RF Developers QA/QC Playbook: From Design to Handover with Verifiable Proof

Executive summary

This article shows how RF Developers will prove build quality end-to-end using Uganda’s Building Control regime, ESIA rules, UNBS materials testing, OSH certifications, and occupation permitting. Every claim maps to a document you can inspect. 

1) Regulatory backbone we follow

  • Building Control Act 2013 and Building Control Regulations 2020: permits, site inspections, stage approvals, occupation permits. 
  • NEMA Environmental & Social Assessment Regulations 2020: ESIA approvals where applicable. 
  • UNBS testing: independent lab tests for materials and systems. 
  • KCCA/Local Authority Occupation Permit before move-in. 
  • OSH permits for workplaces and statutory plant examinations (e.g., lifts, pressure vessels, generators). 
  • Buyer protections: NBRB buyer self-checklist to verify permits, drawings, and as-builts. 
  • Enforcement trend: Parliament signalled tighter penalties and faster appeal paths on delayed permits. 

2) Stage-gated delivery with evidence you can audit

Gate A — Design readiness

Outputs you receive

  • Signed and stamped architectural, structural, electrical, mechanical, plumbing drawings.
  • Proof of competent professionals engaged; permit application pack. 

Evidence file

  • Building permit application acknowledgement.
  • ESIA screening or approval (where required). 

Gate B — Groundworks and structure

Controls

  • Soil investigation and foundation design sign-off.
  • Concrete cube tests and steel rebar verification through an accredited lab. 

Evidence file

  • Lab test reports, batch tickets, site inspection records per Building Control inspection regime. 

Gate C — MEP rough-ins

Controls

  • Electrical, plumbing, fire, and HVAC routing inspected prior to closing works.
  • Statutory plant registered where applicable (e.g., lift installation plan approval and examination). 

Evidence file

  • First-fix inspection certificates and photo log stamped by the Building Control Officer. 

Gate D — Envelope and finishes

Controls

  • Waterproofing tests, window/door performance checks, acoustic checks in premium units.
  • Materials conformity via UNBS or acceptable standards references. 

Evidence file

  • Manufacturer certificates, test summaries, and defect punch-list close-outs.

Gate E — Commissioning and life-safety

Controls

  • Fire alarm, hydrants, pumps, emergency lighting, lifts, generators, and water quality commissioning.
  • OSH statutory examinations for plant, plus Building Control inspections for completion. 

Evidence file

  • Commissioning certificates, OSH plant examination certificates, as-built drawings set. 

Gate F — Legal occupancy and handover

Controls

  • Occupation Permit issued by the local authority.
  • Owners’ files delivered: permits, test reports, warranties, O&M manuals. 

Evidence file

3) The Evidence Vault (what we publish, redacted where needed)

  • Building permit and inspection schedule snapshots. 
  • ESIA approval or exemption letter. 
  • UNBS lab test abstracts for concrete, steel, aggregates. 
  • OSH statutory plant examination certs for lifts and generators. 
  • Occupation Permit and as-builts checklist per NBRB buyer guide. 

4) Snagging, DLP, and warranty policy

  • Joint snag/walkthrough with time-stamped issue log and SLA.
  • Defects Liability Period: RF fixes patent and latent defects within agreed windows; unresolved items may be rectified by buyer with reasonable cost recovery.
  • Warranty matrix: structure, roofs, waterproofing, MEP systems, lifts, finishes; manufacturer terms appended.

5) Service-charge governance after handover

  • Budget and sinking-fund policy disclosed pre-completion.
  • Annual statements and external audits.
  • Common-area asset register with maintenance intervals and vendor roster.

6) Owner’s quick-verify checklist (5 minutes)

Building permit number and final inspection record. 

ESIA certificate or written exemption. 

UNBS test report numbers on concrete and steel. 

OSH certificates for lifts/generators. 

Occupation Permit copy and date. 

7) Transparency and recourse

  • If a local committee delays permits or occupation decisions beyond statutory timelines, buyers can seek review via NBRB appeals; lawmakers have strengthened recourse and penalties for non-compliance. 

8) What this means for buyers

  • You do not rely on promises. You rely on permits, tests, and third-party certificates anchored in Ugandan law and standards. 